Nomad Development Project
Nomad Development Works Works to move the Club up to BLYM are due to start in the next few weeks. Bank improvement works to our sheltered training facility and polo pitch are scheduled to start on Tuesday 27th May. The fencing contractor is scheduled to start on 16th June. Help from all Club Members is needed to support the move. Two Saturday working parties to undertake advanced works prior to the main works starting are planned for: Working party 1 - Saturday 24th May at 10am to 12 noon Preparation of site for bank works including: Recovery of sunken pontoon, Removal of scaffold tubes along bank, Relocation of log seating, General tidy of area. Equipment required: Gloves, wheelbarrows, spades and garden forks Working Party 2 - Saturday 14th June at…