Nomad Development Works

Working party – Saturday 14th June from 10am to 1pm

Bank improvement works to our sheltered training facility and polo pitch started this week and are expected to last for approximately 2 weeks. Whilst these works continue, help from Club Members is required to prepare for the fencing works and relocation of the containers/clubhouse.

There will be a working party this Saturday from 10am to 1pm. Planned works include:

  • Preparation of site boundary in advance of fencing contractor
  • Relocate a 5m section of the bund
  • Some tree lopping activity
  • Preparation for positioning of shipping containers
  • Preparation of ground for positioning of clubhouse

Equipment required: Gloves, wheelbarrows, spades, garden forks, strimmer, rakes, loppers and a chainsaw.

Hope to see as many of you there as possible, many hands make light work!
Thanking you in advance for your help in developing your Club.